Builders seek relief on deadlines; here's what it means for your home's possession date.
Get DetailsThere is a particular kind of anxiety that settles over a homebuyer when the word 'delay' enters the conversation, and this year, that word has found its way into a formal representation from one of Gujarat's most influential builder bodies. The Credai Ahmedabad, representing real estate developers, has requested the Gujarat Real Estate Regulatory Authority (GujRERA) to provide a six-month extension for current housing projects under the force majeure clause of the RERA Act. It is a request rooted not in vague industry grumbling but in a set of very specific, very real pressures that have been building through the year.
The association's case rests on more than one leg. This request is based on the increasing costs of construction, disruptions in supply chains, and shortages of labor. In its formal representation, the association highlighted that the ongoing conflict in West Asia has impacted the supply of crude-related construction materials, thereby hindering project execution and straining financial planning throughout the industry. Ankur Desai, secretary of Credai Ahmedabad, put the difficulty in stark terms, noting that developers are confronted with a situation where both the availability and affordability of crucial construction materials have been affected simultaneously.
The association contends that the current circumstances are beyond the developers' control and warrant relief under Section 6 of the Real Estate (Regulation and Development) Act, which permits the extension of project timelines in cases of force majeure. Beyond the headline ask, Credai Ahmedabad has also urged the regulator to intervene on the supply side itself, pressing GujRERA to help ease the flow of raw materials and address what the association termed artificial price inflation in the market. Labour has compounded the strain too, with the association pointing to a shrinking workforce during the summer months alongside inconsistent material supply, making the comparison to Covid-era disruption feel less like rhetoric and more like a genuine parallel developers are living through again.
Gujarat's request does not exist in isolation. Following a Ministry of Housing and Urban Affairs advisory that classified the West Asia conflict as a 'war' for the purpose of invoking force majeure, several states have already acted. Maharashtra's regulator, MahaRERA, has granted an automatic four-month extension to eligible real estate projects under the Force Majeure provisions of the Real Estate (Regulation and Development) Act, 2016, applying it to projects whose completion dates fall on or after February 28, 2026. Haryana and Telangana have followed with comparable four-month reliefs of their own. Against that backdrop, Credai Ahmedabad's six-month ask is notably more generous than what peer states have secured so far, a gap that will be worth watching as GujRERA weighs its own order.
The underlying cost pressure is not a matter of dispute among market watchers. Realtors add that there has been a 15-30 per cent rise in construction costs since the start of the conflict in February this year, with labour costs seeing a 15-20 per cent hike. Developers, according to industry observers, have already been quietly building four to six month buffers into their own project timelines simply to stay realistic about delivery, regardless of what any regulator ultimately decides.
For a buyer sitting on an under-construction booking in Ahmedabad, this news deserves a measured response rather than alarm. If GujRERA does grant an extension in line with what other states have done, it will typically apply automatically to eligible registered projects without requiring the buyer or even the developer to file individual applications, and any revised completion date will be reflected on the GujRERA portal. It is worth remembering, too, that an extension of this kind does not erase the interest a promoter may already owe for delays incurred before the force majeure window began, nor does it retroactively excuse older lapses. Buyers who are mid-way through a purchase, or considering one, would do well to check the project's current registration status on the GujRERA portal and have a direct conversation with their builder about the realistic handover date rather than relying on assumptions.
Whether GujRERA settles on four months, matches Credai's six-month request, or takes a different position altogether, the episode is a useful reminder of how closely a home's delivery timeline is tied to forces far beyond a single construction site, from crude-linked material costs to a conflict thousands of kilometres away. Staying informed on regulatory decisions like this one is now as much a part of homebuying diligence in Gujarat as checking floor plans or comparing localities.
Bandra East, Mumbai
To be announced • Pricing on request
11-acre railway land, ₹5,400 Cr bid, next to BKC
Juhu, Mumbai
To Be Announced • Price on Request
1.85-acre sea-facing redevelopment
Versova, Andheri West, Mumbai
To be announced • Price on Request
17.18 lakh sq ft MHADA redevelopment
Malabar Hill, Mumbai
3, 4 BHK • Price on request
Cluster redevelopment on Mumbai's most prestigious hill
Worli, Mumbai
Ultra-luxury residences • Price on request
India's first Aman-branded residences
Worli, Mumbai
3, 4 BHK • Price on Request
MHADA redevelopment on Worli Seaface
Bandra West, Mumbai
3, 4, 5 BHK • Price on Request
Sea-facing luxury near Bandra Bandstand
Bandra East, Mumbai
To be announced • Price on request
11-acre railway land, 19.5 lakh sq ft FSI
Fill in your details and our team will get back to you shortly with pricing, availability, and more.
The information here is shared in good faith for guidance alone and forms no part of any agreement. All figures, layouts, and images are subject to revision. Please confirm every detail with an authorised representative before proceeding. About · Projects
Share your details and our expert will call you back.